Scheduling a COMMERCIAL U & O Inspection and Order of Required U & O Inspections

Use and Occupancy (U & O) inspections must be scheduled by DPS staff. Once a Commercial U & O permit has been approved, Zoning will review for Use. Once Zoning approves the Use, the inspections for Fire Protection, Energy Conservation, Electrical, Mechanical and Building will load in the system. NO OTHER INSPECTIONS CAN BE SCHEDULED UNTIL THE FCC INSPECTIONS ARE APPROVED. Inspections must be SCHEDULED and MUST be APPROVED in the following order prior to scheduling the next inspection.
Fire Protection Inspection
Energy Conservation
Electrical Inspection
Building and Mechanical Inspection